Active acceptance response strategy
You and your sponsor agree to actively accept the quality risk of using a non-certified engineer on the project. What will you be doing?
A. Nothing. You will only react if the risk event occurs.
B. Find a way to decrease the probability or impact of the risk.
C. Create a contingency plan in the event the risk event occurs.
D. Insure the risk so your company can be compensated if the risk event occurs.