Activity dependencies
During a simple home repair project, Eva is planning on putting two coats of paint on her dining room. After the second coat of paint dries, she intends to hang up a picture of her family in the room. The activity relationships described in this example are known as:
A. Soft logic
B. Lag
C. Mandatory dependencies
D. Critical path