Contract communications
Contracts should typically be communicated through:
A. Informal written
B. Informal verbal
C. Formal written
D. Formal verbal
Answer: C. Formal written
Formal written communication should be used for project documents such as project charters, project plans, and contracts. As a general rule, if it needs sign-off, then you should take a formal written method. Most project communication, however, will fall into the other categories. These could include email (informal written), meetings (informal verbal), and presentations (formal verbal).
Forecasting – time series methods
As the project manager responsible for creating forecasts, you tend to utilize time series methods for predicting outcomes. Reports you typically use are:
A. Monte Carlo simulation, P&I matrix
B. Linear regression analysis, non-linear regression analysis
C. Probability estimates, Delphi method
D. Earned value, moving average
Answer: D. Earned value, moving average
Examples of time series methods are earned value, moving average, extrapolation, linear prediction, trend estimation, and growth curve.
Report Performance process output
The main output of the Report Performance process is:
A. Performance reports
B. Stakeholder register
C. Project charter
D. Communications management plan
Answer: A. Performance reports
Performance reports provide status and progression for the project to various stakeholders.
Identify Stakeholders process output
The main output of the Identify Stakeholders process is:
A. Performance report
B. Stakeholder register
C. Project charter
D. Communications management plan
Answer: B. Stakeholder register
The stakeholder register contains all the details regarding project stakeholders. It is used as an input for other communication processes.
Distribute Information process
What is the only output of the Distribute Information process?
A. Organizational process assets updates
B. Communications management plan
C. Stakeholder register
D. Performance reports
Answer: A. Organizational process assets updates
Organizational process assets updates is the only output of the Distribute Information process.
Stakeholder analysis models
Types of stakeholder analysis models include all of following except:
A. Influence/satisfaction grid
B. Influence/impact grid
C. Power/interest grid
D. Power/influence grid
Answer: A. Influence/satisfaction grid
Common stakeholder analysis models are power/interest grid, power/influence grid, influence/impact grid, and salience mode.
Management skills
When managing stakeholder expectations, a project manager should apply management skills when appropriate. Which of the following is not a management skill?
A. Presentation skills
B. Negotiating
C. Overcoming resistance to change
D. Writing skills
Answer: C. Overcoming resistance to change
Overcoming resistance to change is an interpersonal skill, not a management skill.
Interpersonal skills
When managing stakeholder expectations, a project manager should apply interpersonal skills when appropriate. Which of the following is not an interpersonal skill?
A. Building trust
B. Resolving conflict
C. Active listening
D. Self-motivation
Answer: D. Self-motivation
Motivation of one’s team is an interpersonal skill, but not self-motivation.