Labor cost
While planning your budget, you decide to categorize your types of costs. Labor, the biggest cost on the project, is best categorized as a(n):
A. Fixed cost
B. Variable cost
C. Direct cost
D. Indirect cost
Answer: C. Direct cost
Direct costs are those that attribute directly to a particular project. Conversely, indirect costs typically benefit multiple projects, such as overhead costs. One way to look at fixed costs vs. variable costs is that the former do not change as production changes.
Getting better over time
Part of your project includes building one hundred widgets. You know that it will take longer and be more costly to do the first widget as opposed to the one-hundredth widget because of improved efficiency. This is known as:
A. Historical information
B. Bottom up estimating
C. Learning curve
D. PERT estimating
Answer: C. Learning curve
A learning curve will lead to improved efficiency since your team will be more experienced as they build the widgets. This is a form a parametric estimating.
Opportunity cost
During the project selection stage, you learn that the value of Project A is $100,000 and the value of Project B is $75,000. Ultimately, Project A was chosen. As a result, the opportunity cost of that decision is:
A. $100,000
B. $75,000
C. $25,000
D. $175,000
Answer: B. $75,000
The opportunity cost is simply the value of the project not chosen. There is no math involved.
PERT formula
The PERT formula is typically calculated as:
A. (O+M+P)/6
B. (O+4M+P)/6
C. (O+M+P)/3
D. (O+4M+P)/3
Answer: B. (O+4M+P)/6
PERT is a weighted average, typically with emphasis on the most likely (M). PERT is a weighted average, typically with emphasis on the most likely (M). So if you are going to calculate 1x optimistic plus 4x most likely plus 1x pessimistic, then there are six variables. Therefore, you would divide by six to get a weighted estimate.
CPI and SPI: The under-rated indicators
Six months into a year-long project your CPI is 0.8. However, your SPI is 1.2. This means that the project is:
A. Ahead of schedule and under budget
B. Ahead of schedule and over budget
C. Behind schedule and under budget
D. Behind schedule and over budget
Answer: B. Ahead of schedule and over budget
For both Cost Performance Index (CPI) and Schedule Performance Index (SPI), 1.0 is exactly as planned, over 1.0 is good and under 1.0 is bad. So in this case, the CPI is bad and SPI is good. In this example, the CPI means you are getting $0.80 of value out of every $1 spent (see CPI — what is it trying to tell me?) while the SPI means you are progressing at 120% (i.e. 20% better than planned) of the baseline.
CPI — what does it mean?
As the project manager with a cost conscience sponsor, you have been monitoring earned value throughout the year long project. At the halfway point, you report that the CPI is 0.8. This means that the project is:
A. Ahead of schedule
B. Under budget
C. Behind schedule
D. Over budget
Answer: D. Over budget
The Cost Performance Index (CPI) determines how much value you are earning per $1 spent. A CPI of 1.0 means you are on target and means that for every $1 you are putting into the project, you are getting $1 of value in return. Therefore, a CPI of 1.5 means that you are getting $1.50 for every $1 you put in, which is a good thing. Conversely, a CPI of 0.8 represents only getting $0.80 per $1, not so good. In short, over 1.0 is good, under 1.0 is bad.