Procurement process
Part of your project includes the construction of a new room and although it is not your company’s core competency, you decide to perform a make-or-buy analysis. After you conduct your due diligence and make your decision, you will be creating a request for proposal. Which process are you working on?
A. Plan Procurements
B. Select Sellers
C. Conduct Procurements
D. Plan Contracting
Answer: A. Plan Procurements
The four current processes in the procurement knowledge area are Plan Procurements, Conduct Procurements, Administer Procurements, and Close Procurements. Make-or-buy decisions and procurement documents, such as a request for proposal, are performed in the Plan Procurements process.
Wait, what do you mean our RFP isn’t good?
You released an RFP but several of the prospective suppliers have questions regarding some of the scope. You determine that the best way to listen to their concerns and convey your message is to have a(n):
A. Invitation for bid
B. Qualified supplier list
C. Bidders conference
D. Independent estimate
Answer: C. Bidders conference
A bidders conference is a meeting with suppliers to ensure they have a good understanding of the procurement document.
Contract communications
Contracts should typically be communicated through:
A. Informal written
B. Informal verbal
C. Formal written
D. Formal verbal
Answer: C. Formal written
Formal written communication should be used for project documents such as project charters, project plans, and contracts. As a general rule, if it needs sign-off, then you should take a formal written method. Most project communication, however, will fall into the other categories. These could include email (informal written), meetings (informal verbal), and presentations (formal verbal).
Contract types 101
After deciding to outsource a part of the project, your sponsor tells you that he wants a contract with the least amount of risk. What type of contract will you be seeking?
A. Fixed price
B. Time and materials
C. Cost plus fixed fee
D. Cost plus percentage of cost
Answer: A. Fixed price
Of the contract types listed, fixed price (aka firm fixed price or lump sum) is the safest bet for the buyer. In a fixed price contract for $100,000, the buyer knows exactly what she is getting (assuming the scope is clearly defined) and how much she is paying. If the work actually takes more than $100,000 to deliver, then it rests on the supplier.
Close Procurements process output
An important output of the Close Procurements process is:
A. Ensuring that the seller is satisfied
B. Reporting earned value to the sponsor
C. Negotiating the next contract for the next project
D. Getting formal acceptance of the deliverable
Answer: D. Getting formal acceptance of the deliverable
Deliverable acceptance is a critical piece of organization process assets updates, an output of the Close Procurements process.
Fixed Price with Economic Price Adjustment Contract
Using a Fixed Price with Economic Price Adjustment Contract (FP-EPA) typically protects the:
A. Buyer
B. Seller
C. Buyer and seller
D. Escrow
Answer: C. Buyer and seller
The intention of a Fixed Price with Economic Price Adjustment Contract is to protect both the buyer and the seller from external conditions outside of their influence.
Contractor money problems
While building a new community park, you hired a contractor to complete a small visitor center that includes restrooms, a snack shop, and bulletin boards. You agreed to a fixed price contract payable upon completion of their deliverable. Midway through the project, they contractor informs you that the economy has affected their bottom line and they could use some funds upfront to pay their subcontractors. Which is the following is the best thing for you to do?
A. Insist that you agreed to pay upon completion and are not willing to violate the contract.
B. Negotiate a change to the payment conditions.
C. Pay the contractor for the work accomplished to date.
D. Start the search for another contractor.
Answer: B. Negotiate a change to the payment conditions.
Although paying the contractor for the work accomplished to date seems fair, you would want that detailed in a new contract or addendum. Therefore, the best approach is the negotiate the change first so the new payment conditions, whatever they may be, are documented and approved by both parties.
Time and material contract disadvantage
When hiring a supplier with a time and material contract, one concern to be aware of is:
A. Supplier is not motivated to reduce cost
B. You must have clear scope
C. There is usually an increase in change orders
D. Work can be incomplete or sloppy if they fall behind
Answer: A. Supplier is not motivated to reduce cost
For a time and material contract, there is little to no incentive for the vendor to reduce cost. In fact, the more work there is and the longer the project takes, the more the vendor could earn. The other choices are disadvantages for fixed price contracts.
Fixed price contract disadvantage
When hiring a supplier with a fixed price contract, one concern to be aware of is:
A. Supplier is not motivated to reduce cost
B. Work can be incomplete or sloppy if they fall behind
C. It is only appropriate for small projects
D. Total project cost is unknown
Answer: B. Work can be incomplete or sloppy if they fall behind
When a vendor is working with a fixed price contract, they do their best to keep their cost down. The more they save themselves, the more they profit. Therefore, in the event the vendor falls behind, in efforts to keep their profit margins high, they could reduce the quality of their work.
Contract for project without defined scope
You are the project manager for a utility company. While determining the type of contract with one of your suppliers, you realize that the scope has not been defined yet. Which of the following contract types is your best choice?
A. Firm Fixed Price (FFP)
B. Time and Material (T&M)
C. Cost Plus Fixed Fee (CPFF)
D. Cost Plus Award Fee (CPAF)
Answer: B. Time and Material (T&M)
This type of contract is used when the scope is not well defined. If a fixed price contract were used, change orders would ensue, which would typically lead to a cost overrun. This pay-as-you-go method allows the buyer and seller to work together to progressively elaborate on the project scope.
0 Comments