Collect Requirements process inputs
On a project to build a new corporate intranet, the project manager makes a request that you, her mentor, to help her collect requirements. She lays out a plan and asks you if you prefer to help her with interviewing stakeholders or creating prototypes. However, before deciding, you want to ensure that she is ready to start this step. Which of the following is the most appropriate?
A. Review the WBS to ensure that the tasks are necessary
B. Ask her if which task she needs more guidance with
C. Ensure that the schedule is realistic and can accommodate both tasks
D. Ask her if she has an approved project charter