Contract for project that spans many years
You are the project manager for a utility company. While determining the type of contract with one of your suppliers, you want to pay a simple fee but recognize that the project will take nearly a decade to complete. Which of the following contract types is your best choice?
A. Cost Plus Fixed Fee (CPFF)
B. Time and Material (T&M)
C. Firm Fixed Price (FFP)
D. Fixed Price with Economic Price Adjustment (FP-EPA)