Exploit risk strategy
The project is currently behind schedule and with the goal of catching up, you decide to ensure that you reduce the time. Which of the following is an example of exploiting the risk?
A. Assign the most experienced and most talented personnel on any task.
B. Assign the most experienced and most talented personnel on a critical task.
C. Buy insurance against the delay.
D. Find a logical partner to share the risk with.