You plan on using a project management information system (PMIS) to develop a Gantt chart. One drawback of using a Gantt chart is:
A. Finish dates for each project cannot be manually set
B. WBS outline cannot be represented
C. Relationships between tasks are not displayed
D. Only one resource can be assigned to a task