Lag or lead? Critical path or non-critical path?
Although you got your project schedule approved prior to starting it, your client just moved the target finish date up two days. In order to finish the project two days earlier, which of the following can you apply?
A. Add two days of lag to the critical path
B. Add two days of lag to a non-critical path
C. Add two days of lead to the critical path
D. Add two days of lead to a non-critical path
If you are reading this via email, please click here for the answer.