Lag or lead? Critical path or non-critical path?
Although you got your project schedule approved prior to starting it, your client just moved the target finish date up two days. In order to finish the project two days earlier, which of the following can you apply?
A. Add two days of lag to the critical path
B. Add two days of lag to a non-critical path
C. Add two days of lead to the critical path
D. Add two days of lead to a non-critical path
If you are reading this via email, please click here for the answer.
Related Posts -
Three point estimate While planning a project that has not been accomplished before at the company, your manager asks you to get a three point estimate from Shari, the lead designer. Shari provides you with an optimistic estimate (2 hours), a most likely estimate (4 hours), and a pessimistic estimate (12 hours). What...... -
McGregor's Theory X and Theory Y While interviewing for a project manager position, you are asked which motivation attitude you have, Theory X or Theory Y. You state that your style is closer to the Theory Y approach and because you: A. Encourage team members to realized their own maximum potential B. Prefer to closely monitor...... -
Organizational process assets You are a project manager for a new client. To help you get acclimated more quickly, she directs you to their organizational process assets in the company archives. You know that when you locate that directory, you will likely find: A. Industry standards B. Historical information C. Financial data D....... -
Activity sequencing, part II The intern who will be verifying address labels will not be able to check them until they have obviously been printed. However, you recognize that she does not have to wait until all of the labels have been printed; rather she can begin shortly after the printing of the labels...... -
Cost variance and schedule variance If a project has a Cost Variance (CV) of 1000 and a Schedule Variance (SV) of -1000, what does it mean? A. The project is under budget and behind schedule. B. The project is over budget and ahead of schedule. C. It is impossible to have a negative SV. D.......
- Writing block and tendency to procrastinate while writing my novel, any writers out there with suggestions? I am going into chapter 16 of my novel but have spent the last week basically cruising the web and watching satellite television. I am drawn to movies about writers...
- Get your Five a Day We have all been hearing for our entire lives that we should be eating five servings of fruits and vegetables every day, but this isn't always easy, is it? Our...
- 11 Useful Blogger and WordPress Tweaks, Tips, Tricks and Tools To Improve your Reader Experience Listed below are "11 Useful Blogger and WordPress Tweaks and Tools To Improve your Reader Experience". It will help in enhancing your visitors or readers experience. 80% of these list...
- Web Design Experts Grade MySpace The popular Web site turned "crap into treasure," says one Web design expert. Will that last? By David F. Carr MySpace.com's continued growth flies in the face of much of...
- Top Ten Tips for Guiding a Successful IP Telephony Implementation Top Ten Tips for Guiding a Successful IP Telephony Implementation Often when an organization considers change that will impact every employee— such as an enterprise-wide IP telephony implementation—the process tends...