Level resources
Resource leveling typically results in a:
A. Project cost overrun
B. Project cost savings
C. Project duration longer than the baseline
D. Project duration shorter than the baseline
If you are reading this via email, please click here for the answer.
Gabe,
I hope all is well with you and yours and that you all have a happy, healthy holiday season.
I have a minor nit to pick with today’s question. If you ave not leveled the resources you should not have baselined the schedule. The schedule produced before resource leveling I call a fantasy. So if you call it the initial schedule, rather than the baseline schedule this nit goes away.
I check out the questions everyday I think you are doing a great service to the PM community with the subscription you offer. It is especially helpful to those prepping for the PMP exam. Keep up the good work.
Gary
Thanks for your feedback (and nit!).