Lowest level WBS components
While creating a WBS, Greg is working with his team to break down the work into manageable pieces. Once completed, Greg expects to determine costs and create a schedule using the lowest level WBS components, which are called:
A. WBS activities
B. Organizational process assets
C. Work packages
D. Decomposed tasks