Monitor and control risks tool
While monitoring and controlling risks on a project, one of the tools a project manager could use compares the amount of the contingency reserves remaining to the amount of risk remaining to determine if the remaining reserve is adequate. This is called:
A. Reserve analysis
B. Performance report
C. Risk audit
D. Variance and trend analysis