Perform Integrated Change Control process
After taking a position as a project manager for a new department, you learn that they follow a change control process that maps to the Perform Integrated Change Control process in the PMBOK®. What is the likely scenario when making a change to a project?
A. Document the change request, bring it to a change control meeting, update the change request status
B. Document the change request, notify the manager, notify the customer, make the change
C. Go to a change control meeting, document the change request, make the change
D. Go to a change control meeting, notify the manager, notify the customer, document the change request
If you are reading this via email, please click here for the answer.