Reasons for a change request
A change request should be initiated when any of the following occur except when there is:
A. A different resource is assigned to a task.
B. An error in defining the scope of the product.
C. An error in defining the scope of the project.
D. An new government regulation.
If you are reading this via email, please click here for the answer.
(A) is one correct answer – agreed.
However, there maybe new government regulations that do NOT affect my special project. So (D) also is a correct answer, isn’t it?
So the “correct” answer could be (A) or (D).
-but we only have ONE correct answer, so there is a dilemma-
Good point. The assumption is that the government regulation is related to your project, however.