Reducing project duration with cost in mind
Dwight’s project is behind schedule. As a result, he is looking to reduce the duration of his project to bring it back on track. Dwight is also tasked with keeping costs as low as possible to reduce the risk of an overrun. What tactic should he use?
A. Fast-track
B. Critical path
C. PERT
D. Crash
If you are reading this via email, please click here for the answer.