Sequence Activities process
As a senior project manager, Jim is asked to review the work of other project managers in the organization. Wendy, a fairly new project manager, is working with her team to sequence activities. One thing Jim should ensure is that Wendy has already performed the __________ process.
A. Develop Schedule
B. Estimate Activity Resources
C. Define Activities
D. Estimate Activity Durations