CPI and SPI: The under-rated indicators
Six months into a year-long project your CPI is 0.8. However, your SPI is 1.2. This means that the project is:
A. Ahead of schedule and under budget
B. Ahead of schedule and over budget
C. Behind schedule and under budget
D. Behind schedule and over budget
Answer: B. Ahead of schedule and over budget
For both Cost Performance Index (CPI) and Schedule Performance Index (SPI), 1.0 is exactly as planned, over 1.0 is good and under 1.0 is bad. So in this case, the CPI is bad and SPI is good. In this example, the CPI means you are getting $0.80 of value out of every $1 spent (see CPI — what is it trying to tell me?) while the SPI means you are progressing at 120% (i.e. 20% better than planned) of the baseline.
CPI — what does it mean?
As the project manager with a cost conscience sponsor, you have been monitoring earned value throughout the year long project. At the halfway point, you report that the CPI is 0.8. This means that the project is:
A. Ahead of schedule
B. Under budget
C. Behind schedule
D. Over budget
Answer: D. Over budget
The Cost Performance Index (CPI) determines how much value you are earning per $1 spent. A CPI of 1.0 means you are on target and means that for every $1 you are putting into the project, you are getting $1 of value in return. Therefore, a CPI of 1.5 means that you are getting $1.50 for every $1 you put in, which is a good thing. Conversely, a CPI of 0.8 represents only getting $0.80 per $1, not so good. In short, over 1.0 is good, under 1.0 is bad.
Calculating Schedule Performance Index (SPI)
If EV = 25,000, PV = 30,000, and AC = 29,000, what is the SPI?
A. 0.83
B. 0.86
C. 1.16
D. 1.20
Answer: A. 0.83
SPI (Schedule Performance Index) is calculated by EV (Earned Value)/PV (Planned Value). The 0.83 means that the project is progressing at 83% of the baseline.
Calculating Cost Performance Index (CPI)
If EV = 25,000, PV = 30,000, and AC = 29,000, what is the CPI?
A. 0.83
B. 0.86
C. 1.16
D. 1.20
Answer: B. 0.86
CPI (Cost Performance Index) is calculated by EV (Earned Value)/AC (Actual Cost). The 0.86 means that the project is getting 86 cents out of every dollar.
How much more the project is expected to cost from here on out
You are halfway through your project and your sponsor would like to know how much more the project is expected to cost from now until the end. What earned value metric should you use?
A. CV
B. AC
C. EAC
D. ETC
Answer: D. ETC
ETC (Estimate to Complete) tells you that the project is expected to cost x dollars to complete. This is derived from how much the project is expected to cost currently (EAC) and how much was already spent (AC).
Calculating Schedule Variance (SV)
If EV = 25,000, PV = 30,000, and AC = 29,000, what is the SV?
A. -5,000
B. -1,000
C. 1,000
D. 5,000
Answer: A. -5,000
SV (Schedule Variance) is calculated by EV (Earned Value) – PV (Planned Value). The -5,000 means that the project is behind schedule.
Calculating Cost Variance (CV)
If EV = 25,000, PV = 30,000, and AC = 29,000, what is the CV?
A. -1,000
B. -4,000
C. 1,000
D. 4,000
Answer: B. -4,000
CV (Cost Variance) is calculated by EV (Earned Value) – AC (Actual Cost). The -4,000 means that the project is $4,000 over budget.
How much the project is expected to cost at completion
You are halfway through your project and your sponsor would like to know how much the project is expected to cost when it is completed. What earned value metric should you use?
A. CV
B. AC
C. EAC
D. ETC
Answer: C. EAC
EAC (Estimate at Completion) tells you that the project is expected to cost x dollars. This is derived from how much you thought it would cost from the beginning (BAC) and what the rate of spending is (CPI).
SPI — what does it mean?
As the project manager with a time conscience sponsor, you have been monitoring earned value throughout the year long project. At the halfway point, you report that the SPI is 0.8. This means that the project is:
A. Ahead of schedule
B. Under budget
C. Behind schedule
D. Over budget
Answer: C. Behind schedule
The Schedule Performance Index (SPI) determines how much ahead or behind schedule you are. An SPI of 1.0 means you are on target. Therefore, an SPI of 1.5 means that you are progressing at 150% of the baseline, which is a good thing. Conversely, an SPI of 0.8 represents only moving at 80% of the baseline, not so good. In short, over 1.0 is good, under 1.0 is bad.
Earned value chart
At your upcoming status meeting with your project sponsor, rather than just using a table, you want to graphically show earned value. Which of the following charts will you use?
A. Trend analysis
B. Control chart
C. S-curve
D. Pareto diagram
Answer: C. S-curve
An S-curve graph typically displays earned value (EV), planned value (PV) and actual cost (AC). PV is charted first and will look like an S. As time progresses, the EV and AC will extend allowing you to compare them against the PV.
0 Comments