Transfer risk response strategy
A good example of transferring a negative risk is:
A. Hiring another contractor to accelerate a project
B. Replacing a new employee with a more experienced one to ensure better quality
C. Buying insurance against weather impacting a construction schedule
D. Starting a task a few days earlier on the critical path
If you are reading this via email, please click here for the answer.