During the planning phase of your project, you are working closely with your team to put the finishing touches on the initial work breakdown structure (WBS). As your last step, you add a unique identifier to each work package so it can be used to monitor scope, time and cost later in the project. These unique identifiers are commonly known as:
A. Milestones
B. WBS dictionary
C. Outline system
D. Code of accounts