Which project requires Close Project tasks?
Of the following projects, which would not require you to complete Close Project tasks immediately?
A. A construction project that was completed
B. A construction project that was put on hold during the execution phase
C. A software project that was canceled during the execution phase
D. A software project that was canceled just during the planning phase